See our previous work

Previous Projects

Australian Tanks has a proven track record

At Australian Tanks we value service and the quality of our products. Thanks to our extensive range we can meet the most stringent requirements found on your site.

See examples of our work below and contact us if you have any questions. Sign-up to the Engineers Hub to download our CAD drawings.

With a growing number of writing services on the internet, it is essential to determine which sites are legitimate and reputable. A legit nursing paper writing service will pass a quality, security, and confidentiality test. https://mynursingpaper.net service will come with accompanying papers to show their legitimacy. A student should always conduct due diligence before settling for a writing service. Check out their reviews online to see whether they have a good reputation.
Tallawarra B Power Station Expansion
Australian Tanks worked with Clough and Energy Australia to provide a detergent wash water effluent holding tank for Tallawarra B Power Station Expansion in Illawarra, NSW.
22 Kiln st, Darra, Qld
Australian Tanks teamed up with CIP to design and install 30 Parthenon modules at 22 Kiln St, Darr, Queensland.
The storm-water detention system was to be installed in the driveway and would impact access to the site to a fast and effective solution was required.
Kiln St, Darra
Australian Tanks teamed up with Hutchinson Builders and ADG Engineering to install 1.4 Million litres of stormwater detention at Kiln St in Darra Queensland.
University of Sunshine Coast
Australian tanks teamed up with Jolex and Badge Construction to create a solution to the University of Sunshines Coasts’ water retention program.
Tile Street Detention system
Australian Tanks teamed up with Vaughn Construction and VTCE to provide an on-site detention system that met the filtration requirements.
Residential development – Denman Prospect ACT
A unique hybrid installation combining both water retention and water detention.
Coomera Town Centre South
Australian Tanks teamed up with Civil 360, Golding Contractors and Foxwellat the new Coomera Town Center South, 64 Foxwell rd, Coomera.
Platinum Hydraulic Design
Platinum Hydraulics were commissioned by Christopher Contracting Plumbing & Drainage to provide the hydraulic design for the Trade Waste Arrestor package for the new Westfield Coomera Shopping Centre precinct in South East Queensland.
Bloomer Constructions
With these Sewer Holding Chambers provided on the plan as build-on-site, the unique site requirements proved this solution to be unworkable in time and cost efficiencies.
Enviro Pacific
Enviro Pacific, contractor for a new 7Eleven fuel station at The Gap (Qld), contracted Australian Tanks (ATQ) to supply a 20,000L trafficable and anti-floatation blind sump tank to capture stormwater run-off contaminated with fuel from the area ssurrounding fuel bowsers. With no tank specified on the plans, Enviro Pacific sought a solution which met all industry standards and one which would be approved by 7Eleven.
Hutchinsons Builders
With stormwater run off from surrounding sites, a rapid install was essential. Combined with budget constraints, a cost efficient solution was required for project maximisation.
Accurate Plumbing
Previously, Accurate Plumbing (the Plumbing Contractor) had installed up to 30 pump stations using an alternative system over a 12-18 month period. The pump stations were challenged with speed issues and OHS requirements, further impacted by the cost and time loss incurred by ongoing replacement and servicing.
Reidy Constructions
Australian Tanks provided a 20kPa load rated precast concrete tank that was designed to be trafficable by a fully loaded semi-trailer.
The pump equipment, including all the pipework, valves, upper guide bar brackets, guide rails, discharge connections, pumps, pump lifting chains, and float switches, were fitted in the tank in the Australian Tanks factory.
SJ Higgins for McDonalds Australia
McDonalds Australia Limited engaged SJ Higgins to construct two new McDonalds Restaurants in Oxenford and Chermside Park. Torque Civil (Oxenford) and Blue Frog Plumbing (Chermside) were appointed to provide the Hydraulic Packages. Both stores had Humes Rain vaults and Volume Filters as part of the package. Australian Tanks were engaged to provide an equivalent solution to these rain harvesting requirements specified in the plans.
John R Keith Group
John R Keith (Plumbing Contractor and our client) approached Australian Tanks to offer an alternative solution to the more expensive extra heavy duty tank option which was specified in the Hydraulic plans. The original option in the plans also showed (1) a combination of transport cost challenges, (2) requiring additional work to get the initial tanks rated to take heavy traffic loads, and (3) the need to have considerable cover over the tanks to meet Invert Levels for the site.
Beavis & Bartels Pty Ltd
Project required 150,000L water storage for reuse at the Aldi Brendale distribution centre truck wash bay.
Civilivic, Stormwater Detention
Situated beneath a shared driveway, this 42,000L stormwater detention site presented multiple requirements in project time and cost efficiencies. The site could not be shut down for two weeks for an in-situ solution, therefore an anti-floatation and heavy duty trafficable Australian Tanks precast solution with a one-day install time was the most efficient process available.
Dean Ash Construction
This large 135,000L stormwater detention system required multiple efficiencies in time and cost – located under a roadway, it was essential to ensure both a trafficable and anti-floatation system within a 24 hour timeframe.
Hutchinsons Builders – Toowoomba
By urgent request, Australian Tanks were appointed to provide an underground, trafficable detention system and to have the system fully installed within a 24 hour period.
DEQ Consulting Engineers
Australian Tanks were specified on plan to provide 2 x 133,000L underground trafficable detention systems. Both systems required multiple efficiencies in install time and site costs. Located under a thoroughfare road, it was essential to have prompt delivery with lowering and positioning of the tanks a priority to avoid construction delays and OHS issues with an open excavation for any extended period of time.
OM Civil Pty Ltd
ATQ provided a proposal for this project in 2018, securing the job following an extended hold on the site commencement date.

With a very tight time frame involved to get the site construction ready, there was only one day available for the onsite install of the ATQ underground systems.
FAL Construction – Edmonson Park
ATQ was specified by the engineers on this job. Through this channel, ATQ was approached by FAL Construction for the first time and right at the start during the tender stage.

All our product specs any time.

Are you planning for an upcoming project? Our Engineer’s Hub can help you find the product you need, quickly and easily.

Every detail is here for you when you need it, at your own leisure, to help you discover what is the right fit for your project.

Gain access to all the required plans to determine which product meets your needs and be able to specify the solution into your design with downloadable CAD drawings.

Complete access to all our documents