Hutchinsons Builders
Stormwater Detention - Toowoomba, Qld
Challenge
By urgent request, Australian Tanks were appointed to provide an underground, trafficable detention system and to have the system fully installed within a 24 hour period.
Solution
- Three (3) x precast 7000L tanks provided as an inter-connectable stormwater detention system
- Installed in just one (1) hour and fifteen (15) minutes
Result
- Fully installed by 1:20pm with a two-man crew
- Trafficable by a fully loaded semi-trailer, based on the SM1600 traffic design load ratings
- Onsite efficiencies and project savings
Products
- Australian Tanks 7000L (x 3) inter-connectable precast tanks
- All penetrations, risers and access frames
- All sealant supplied for installation
- Extra Heavy Duty for SM1600 traffic design load ratings